BOD and suspended solids removal from town sewage with abattoir discharges by aerated ponds
A small rural treatment plant in Catalonia, in operation since 1989, treats sewage from about 7,000 inhabitants mixed with the treated effluent and waste sludge of the activated sludge plant of an abattoir that processes up to 3,000 pigs a day. Before September 1993 the abattoir's raw wastewater went straight into the sewer; since then its own plant has discharged effluent and sludge instead.
Treatment line
- 01Fine screenFollowed by a flume that measures the flow.
- 02Primary aerated pond4,050 m² and 4 m deep, with a small settling area whose three pumps return biomass to the pond inlet or send settled sludge to the third pond.
- 03Secondary aerated pond4,050 m² and 4 m deep.
- 04Tertiary sedimentation pond4,050 m² and 3.5 m deep; acts as a large clarifier where discharged sludge settles, and sludge is wasted from it.
- 05Quaternary sedimentation-maturation pond2,950 m², half a 3.5 m deep settling area and half a 1 m deep maturation area.
What the source found
After the abattoir built its own plant, effluent quality and reliability improved markedly; on the monthly grab samples the ponds removed 96% of BOD and 94% of suspended solids, although these morning samples overstate the inlet BOD and so the BOD removal. Sludge discharges, even far above the design loads, did not worsen the effluent, because the long retention time lets the sludge settle in the later ponds. They did, however, raise sludge production well above a similar nearby plant and increase operating costs.
Monthly grab samples of inlet and outlet from March 1989 to January 1998, of which the figures shown are the averages after September 1993; two campaigns in 1997 and 1998 added three to four samples a week, with 24-hour flow-weighted inlet samples, after large sludge discharges.
Water in, water out
| Parameter | Symbol | Unit | Inlet | Outlet | Removal |
|---|---|---|---|---|---|
| Flow rate | m3/d | 3,000 | |||
| Total suspended solids | TSS | mg/l | 370 | 24 | 94% |
| BOD5 | BOD5 | mg/l | 385 | 15 | 96% |
Inlet: influent sewage of the plant. Outlet: final effluent of the pond system. Averages of monthly grab samples taken after September 1993 up to January 1998. Values and units are as the published source prints them. Removal is worked out from the two values, or is the source's own figure where it prints no pair.