COD removal from slaughterhouse wastewater by an upflow anaerobic sludge blanket reactor
A small upflow anaerobic sludge blanket reactor was set up at a municipal slaughterhouse in Huancavelica, at about 3,715 m altitude, whose existing treatment plant was poorly sized, unmaintained and discharging a dark grey effluent. The slaughterhouse wastewater passed the existing coarse screen and grit chamber and was pumped into a 350 litre storage tank, which fed the reactor at a constant rate. The figures cover the reactor alone, from its inlet to its outlet.
Treatment line
- 01Upflow anaerobic sludge blanket reactorPolyethylene reactor of 29 litres, seeded with anaerobic sludge and fed about 50 litres a day for a 14 hour retention time, later also tested at 12 hours.
What the source found
At 14 hours of retention the reactor removed on average 49% of COD, ranging from 32% to 77%, while at 12 hours the average fell to 38%, so the reactor was returned to 14 hours. Oil and grease fell by about 17%. The modest COD removal was put down to low ambient temperatures, a retention time that may be too short and a short 30 day start-up.
COD measured at the reactor inlet and outlet on 23 days at 14 hours and 10 days at 12 hours of retention over 115 days of operation from May 2017, with suspended solids and oil and grease analysed at a laboratory in August 2017.
Water in, water out
| Parameter | Symbol | Unit | Inlet | Outlet | Removal |
|---|---|---|---|---|---|
| Total suspended solids | TSS | mg/L | 709.49 | 623.76 | |
| Oil and grease | O&G | mg/L | 33.32 | 27.64 | 17% |
| COD | COD | 49% |
Inlet: wastewater entering the anaerobic reactor. Outlet: wastewater leaving the anaerobic reactor. Pilot reactor at 14 hours of retention; solids and oil and grease are averages of a laboratory analysis in August 2017, COD removal is the average over the 14 hour days. Values and units are as the published source prints them. Removal is worked out from the two values, or is the source's own figure where it prints no pair.