Engineering, Consulting & Financing

    EPC Water Contractors

    Engineering, procurement and construction contractors delivering turnkey water and wastewater treatment plants under fixed-price EPC contracts.

    3 providers

    This page is a good fit if you need:

    • Reverse Osmosis (RO) or Advanced Oxidation Processes (AOPs) capabilities
    • Suppliers with chemicals-pharmaceuticals sector experience
    • Providers operating in Belgium or China
    Providers
    3
    Verified
    0
    Countries
    3

    Can't find the right fit? Post a brief and let qualified suppliers come to you.

    Post a project

    Find a EPC Water Contractors Provider

    Showing 1-3 of 3

    3 results from 3 matched providers

    Liquid X logo

    Liquid X

    Verified
    United Arab Emirates1-50 employees
    Granular Activated Carbon (GAC) Filters · GO–Polymer Composites · Cartridge Filters
    mea

    Liquid X is a water technology consultancy and commercialization platform focused on accelerating the deployment of next-generation filtration solutions, with a core emphasis on graphene-based water treatment. Founded to address the gap between breakthrough innovation and real-world implementation, Liquid X operates at the intersection of advanced material science, water infrastructure, and market deployment. While significant advances in water technologies exist globally, many remain confined to laboratories or early-stage ventures. Liquid X bridges this gap by identifying, validating, and commercializing high-impact solutions—particularly graphene-based filtration systems—within the GCC and wider MENA region. Our consultancy model is built around a full lifecycle approach: from technology scouting and technical evaluation to pilot design, validation, and scaled deployment. We work with asset owners, governments, and enterprises to translate emerging technologies into practical, site-ready solutions. This includes designing pilot programs with measurable performance metrics, enabling data-driven decision-making, and ensuring that innovations are proven under real operating conditions before scale-up. A key focus of Liquid X is the commercialization of graphene-based water filters. Graphene, a two-dimensional material with exceptional strength, permeability, and adsorption capacity, has the potential to fundamentally transform water treatment. Its nano-scale structure allows precise separation of contaminants while enabling faster water flow and lower energy consumption compared to conventional systems. Through strategic partnerships with innovators, researchers, and manufacturers, Liquid X is actively working to bring graphene filtration technologies from concept to market. These systems are being developed to address some of the most critical water challenges, including the removal of PFAS and emerging contaminants, heavy metals, dissolved solids, and industrial pollutants—while significantly reducing waste and energy intensity associated with traditional technologies such as reverse osmosis. Our role extends beyond technology development. Liquid X supports the full commercialization journey, including: Technical due diligence and performance validation Pilot implementation and third-party verification Integration with existing infrastructure Development of scalable deployment models Coordination with EPC contractors, facility managers, and regulators Ongoing monitoring, compliance, and optimization By operating as a vendor-agnostic platform, we ensure that solutions are selected based on performance, suitability, and long-term value—not vendor bias. The MENA region faces some of the world’s most acute water challenges, including scarcity, high desalination dependence, and rising energy costs. Liquid X is positioned to introduce more efficient, decentralized, and sustainable alternatives through advanced filtration technologies. Graphene-based systems, in particular, offer the potential for lightweight, modular, and energy-efficient treatment solutions that can be deployed at scale across residential, commercial, and industrial applications. At its core, Liquid X is not just a consultancy—it is an enabler of the next generation of water infrastructure. By combining deep regional expertise with global innovation networks, we are helping transform how water is treated, distributed, and consumed. Our mission is to accelerate the transition from legacy, resource-intensive systems to smarter, more sustainable water solutions—unlocking the full potential of graphene and other advanced materials to build a more water-secure future.

    Activated Carbon Filtration
    Nanofiltration (NF) Systems
    Point-of-Use (POU) Filtration Systems
    +11 more
    food-beverages
    hospitality-tourism
    EE

    Eragon Enviro Tech. (Xiamen) Co., Ltd.

    Verified
    China51-200 employees
    Reverse Osmosis (RO) · Inclined Plate Settlers (Lamella Clarifiers)
    china · apac · europe

    Eragon Enviro Tech (Xiamen) Co., Ltd. is a specialized provider of industrial water and wastewater treatment solutions, supporting engineering teams, EPC contractors, and industrial clients in solving complex water challenges. We focus on process design, system integration, equipment manufacturing, and modular system supply for industrial wastewater treatment, water reuse, ultrapure water (UPW), and advanced ZLD/MLD applications. Our solutions are applied across semiconductor, electroplating, electronics, and new energy industries, as well as other industrial sectors dealing with complex wastewater streams. We help clients improve system reliability, optimize process stability, reduce operational risks, and meet stringent discharge and reuse standards in demanding industrial environments. With in-house engineering capability and manufacturing strength, we support global partners from design to execution for high-performance water treatment systems.

    mining-quarrying
    chemicals-pharmaceuticals

    Selecting EPC Contractors for Water and Wastewater Projects

    EPC (Engineering, Procurement, Construction) contracting transfers single-point responsibility for design, equipment supply, civil works, installation, commissioning, and performance to one contractor on a fixed-price, fixed-schedule basis, typically under FIDIC Silver Book (turnkey), Yellow Book (plant and design-build), or proprietary lump-sum-turnkey contracts. Water-sector EPC values typically run 5M to 2B-plus USD for full plants; performance guarantees cover effluent quality, energy consumption, chemical consumption, throughput, and availability (typically 95 to 98 percent) for a defined warranty period (commonly 24 months from PAC plus a 12-month DLP). Liquidated damages for delay typically capped at 10 to 15 percent of contract value; for performance shortfall at 10 to 20 percent.

    EPC contractor capability is assessed on: (1) financial capacity, bonding capability typically 110 to 125 percent of contract value (advance payment, performance, retention bonds), audited financials showing turnover at least 3x contract value; (2) technical track record, 3-plus comparable plants commissioned in the last 7 years with reference contacts; (3) process technology, in-house IP or named technology partner (membranes, biological processes, controls); (4) construction methodology, own-fleet for civil works above 20M USD, subcontract management for specialist trades; (5) HSE record, TRIR under 0.5, LTIFR under 0.2, no fatalities in last 24 months; (6) project-management depth, PMP-certified team, document-management system, schedule-baseline rigor (Primavera P6 Level 4).

    Aguato lists EPC water contractors across global tier-1 (Veolia, Suez, Acciona Agua, ACWA Power, IDE Technologies, Aqualia, Doosan Heavy, Hyflux successors), regional specialists, and process-technology-led EPC players. Procurement best practice: shortlist 4 to 6 prequalified contractors, run a 2-stage tender (technical first, commercial sealed), align contract on FIDIC plus project-specific Particular Conditions, structure milestone payment schedule heavy on completion (not mobilization), and require a Daily Construction Report system with named QA and QC sign-off authority.

    Frequently Asked Questions

    FIDIC Silver Book or Yellow Book for a water-treatment EPC?

    Silver Book (EPC/Turnkey, 2017) gives owner full risk transfer at higher premium (5 to 15 percent above Yellow Book): appropriate when owner wants minimal involvement in design and the project risk profile suits fixed-price (mature technology, well-defined site). Yellow Book (Plant and Design-Build, 2017) suits projects where owner specifies performance and contractor designs to meet it, with a more balanced risk allocation: most water EPCs sit here. Avoid Red Book (Construction by Employer Design) for EPC: it shifts design risk back to owner. Always engage FIDIC-experienced Engineer or PMC to administer the contract regardless of which book.

    What performance guarantees should I require?

    Effluent quality (BOD, COD, TSS, nutrients, pathogens) at the agreed reference feedwater: guaranteed for the warranty period with daily-grab plus composite-sampling protocols. Energy consumption (kWh per m3) at design throughput with defined feedwater conditions. Chemical consumption (kg per m3) per chemical with documented dose-response curves. Plant availability at least 95 percent measured over a rolling 90-day window. Each guarantee should have specific liquidated-damages multipliers (USD per percent shortfall) and a cap (typically 10 to 20 percent of contract value). Test protocol (typically 72-hour continuous plus 30-day reliability run) should be in the contract, not deferred to commissioning.

    How do I structure the EPC payment schedule?

    Best-practice milestone schedule for a 50M USD water EPC: 10 percent advance against bank guarantee; 15 percent engineering completion (design 80 percent, procurement orders placed); 30 percent civil works (foundation pour, basin walls, electrical building); 25 percent mechanical and E&I installation (pumps installed, MCC energized, instruments looped); 10 percent commissioning plus performance test passed (PAC); 7.5 percent reliability run completion; 2.5 percent defect-liability completion at end of DLP. Retention 10 percent of each milestone held until PAC, released 50 percent at PAC and 50 percent at end of DLP. This structure aligns cashflow to value delivered and protects the owner against late-stage default.

    What is the typical EPC contract duration for a water-treatment plant?

    Greenfield 50,000 m3 per day drinking-water plant: 24 to 30 months from Notice to Proceed to Provisional Acceptance (PAC). Greenfield 100,000 PE wastewater plant: 28 to 36 months. Large SWRO plant (above 200,000 m3 per day): 30 to 42 months. Industrial ETP under 10,000 m3 per day: 12 to 18 months. Add 12-month Defects Liability Period (DLP) and 5 to 10 year O&M handover. Schedule risks concentrate in: (1) civil critical-path (rebar shortage, weather, geotechnical surprises); (2) long-lead equipment (membranes 16 to 28 wk, large blowers 32 to 40 wk, GIS switchgear 36 to 48 wk in 2025); (3) regulator commissioning approvals. Build 10 to 15 percent schedule contingency into baseline.

    Case Study·Municipal water supply
    Challenge

    A Midlands water company needed a new 40 MLD groundwater treatment works to address iron, manganese, and elevated ammonia from a chalk aquifer source. The company lacked in-house EPC management capability and required a single-point responsible contractor for design, construction, and a 24-month performance demonstration period.

    Approach

    Appointed a UK-based water EPC contractor through a two-stage PQQ and ITB process under a FIDIC Yellow Book 2017 contract with Particular Conditions. The contractor delivered aeration towers, pressure greensand filtration, chlorination, and UV disinfection on a 28-month programme with a 100 kGBP per week LD for delay and performance guarantees on effluent iron (below 20 ug/L), manganese (below 5 ug/L), and ammonia (below 0.05 mg/L). A 10 percent retention was held until end of the 24-month performance demonstration.

    Outcome

    Plant commissioned at 27 months from NTP. Performance acceptance test passed at month 29: all parameters within guarantee limits at first test. DWI accepted the commissioning documentation and authorised supply from the new source. EPC cost 8.2M GBP, within the 8.5M GBP contract price. LD mechanism not triggered. Performance demonstration completed without major defects.

    Questions to Ask Shortlisted Providers

    1. 1

      What is your bonding capacity, and from which A-rated banks or sureties can you provide advance payment, performance, and retention bonds at 110 percent of contract value?

      Bond capacity is the first test of an EPC contractor's financial strength. A contractor who cannot provide bonds from A-rated institutions (Lloyds, major clearing banks, specialist sureties) either lacks the financial standing or is over-extended on other contracts. Bonds protect the client against contractor insolvency during a multi-year construction programme.

    2. 2

      What specific process technology will you use for our treatment objectives, and is it proprietary or third-party licensed, and who is the process guarantor?

      EPC contractors without proprietary process technology rely on subcontracted technology partners. Understanding who is giving the process guarantee (the EPC contractor, the technology licensor, or a joint-and-several arrangement) determines the enforceability of the performance guarantee if the plant fails to meet consent standards.

    3. 3

      What are your TRIR and LTIFR statistics for the last 3 years, and have you had any fatalities on water infrastructure projects?

      Water infrastructure EPC sites are high-hazard: confined spaces, working near live water, excavations, lifting operations. A contractor with TRIR above 1.0 or any fatality in the last 3 years should provide a detailed explanation before being shortlisted. HSE enforcement action or improvement notices are disqualifying factors for most UK water company procurement policies.

    4. 4

      What is your document management system, and how will you structure the ITP, RFI, and NCR management process for a Ofwat-regulated project?

      Ofwat-funded projects require robust quality records for regulatory audit. A contractor who manages ITPs, RFIs, and NCRs through email and spreadsheets rather than a structured document management system (Aconex, Procore, BIM 360) generates audit risk and slows dispute resolution. Confirm the DMS platform and the quality manager's qualifications (CQI Practitioner or equivalent).

    5. 5

      What long-lead items have you identified, and what are your committed procurement timelines for membranes, blowers, switchgear, and instrumentation in 2025?

      Long-lead equipment is the most common cause of EPC schedule overrun in 2025. Membrane elements have 16 to 28 week lead times; GIS switchgear 36 to 48 weeks; turbo blowers 32 to 40 weeks. A contractor who has not already begun procurement enquiries at tender stage has likely not adequately scoped the schedule risk.

    What Drives Cost in This Category

    Technology complexity and proven performance risk

    A standard iron and manganese removal plant (aeration plus greensand plus chlorination) costs 1,800 to 2,800 GBP per m3/day capacity. Adding advanced treatment (GAC, UV-AOP, membrane filtration) for PFAS, pesticides, or disinfection by-products adds 40 to 80 percent to CAPEX. Contractors price a technology risk premium of 5 to 15 percent on novel or first-of-type processes.

    Civil works proportion of total contract

    Civil works (earthworks, concrete structures, pipework, M&E containment buildings) typically represent 35 to 50 percent of water EPC cost. Sites with poor ground conditions (made ground, soft clays, high water table) add 10 to 30 percent to civil scope. Ground investigation before EPC tender minimises ground-risk contingency pricing by the contractor.

    Performance guarantee structure and LD exposure

    Stringent performance guarantees with high LD rates (above 50,000 GBP per week for delay and per percent shortfall for performance) attract a contractor risk premium of 3 to 8 percent of contract value. Calibrating LDs to actual client losses (regulatory penalties, alternative supply costs) rather than punitive levels results in lower pricing and more rational risk allocation.

    Import content and supply chain risk in 2025

    Membrane modules (predominantly supplied from Japan, South Korea, and USA), GIS switchgear (Switzerland, Germany), and specialist instruments (Germany, USA) are subject to currency risk and supply chain delays. At 2025 GBP/USD exchange rates and current lead times, UK EPC contractors are pricing 8 to 15 percent foreign exchange and supply chain risk into fixed-price lump sums.

    Key Regulations & Standards

    Utilities Contracts Regulations 2016 -- Water Company Procurement Obligations

    UK water companies are 'utility entities' under the Utilities Contracts Regulations 2016 (UCR 2016) and must procure EPC contracts above the relevant threshold (approximately 5.3M GBP for works as of 2024) through a competitive procurement process published on the Find a Tender Service. Direct award or sole-source procurement requires documented justification and risks challenge and contract ineffectiveness.

    CDM Regulations 2015 -- EPC Contractor as Principal Contractor

    The EPC contractor on a water infrastructure project is the Principal Contractor under the Construction (Design and Management) Regulations 2015 for the construction phase. The Principal Contractor must: produce the Construction Phase Plan, coordinate construction H&S, notify HSE of notifiable projects (F10), and compile information for the Health and Safety File. The water company as client retains the duty to appoint a Principal Designer.

    WS(WQ)R 2016 -- DWI Commissioning Acceptance

    New or materially altered drinking water infrastructure cannot be brought into supply without DWI (Drinking Water Inspectorate) acceptance of the commissioning documentation. The EPC contractor must provide: process validation data, performance test results against WS(WQ)R 2016 parameters, chlorination records, disinfection validation (CT calculations for UV), and as-built drawings. DWI may require a supervised commissioning run before granting authorisation to supply.

    FIDIC Yellow Book 2017 -- Contract Administration and Performance Testing

    FIDIC Yellow Book 2017 is the standard contract for plant and design-build EPC projects in the UK water sector. Key provisions: Clause 4.1 (Contractor general obligations including performance guarantee), Clause 9 (Tests on Completion including 72-hour performance test and reliability run), Clause 11 (Defects Liability Period, typically 12 to 24 months), and Clause 19 (Force Majeure for supply chain disruptions). The Engineer under FIDIC has specific neutrality obligations under Clause 3.7.